document.write( "Question 751547: Given the activity mean = 5 and Standard Deviation =1 , Find the probability that the project will take more than 10 weeks to complete \n" ); document.write( "
Algebra.Com's Answer #457264 by stanbon(75887)\"\" \"About 
You can put this solution on YOUR website!
Given the activity mean = 5 and Standard Deviation =1 , Find the probability that the project will take more than 10 weeks to complete
\n" ); document.write( "----
\n" ); document.write( "z(10) = (10-5)/1 = 5
\n" ); document.write( "----------
\n" ); document.write( "P(x >= 10) = P(z >= 5) = 0.0000002871
\n" ); document.write( "================
\n" ); document.write( "Cheers,
\n" ); document.write( "Stan H.
\n" ); document.write( "================