document.write( "Question 65061: If 6 men can do a piece of work in 4 days, how many men are needed to do the work in 21 days? \n" ); document.write( "
Algebra.Com's Answer #45594 by ankor@dixie-net.com(22740)\"\" \"About 
You can put this solution on YOUR website!
If 6 men can do a piece of work in 4 days, how many men are needed to do the work in 21 days?
\n" ); document.write( ":
\n" ); document.write( "Since they are doing an equal job
\n" ); document.write( "21x mandays = 4*6 mandays
\n" ); document.write( ":
\n" ); document.write( "21x = 4*6
\n" ); document.write( "21x = 24
\n" ); document.write( "x = 24/21
\n" ); document.write( "x = 1.143 men
\n" ); document.write( ":
\n" ); document.write( "1 man if he skips a few coffee breaks