document.write( "Question 736958: How long will it take 4 workers to complete a task, given that it takes 6 days for 6 workers to complete the same task?
\n" ); document.write( "
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #450064 by Simnepi(216)\"\" \"About 
You can put this solution on YOUR website!
6 days for 6 workers means the job takes 36 (6X6) 'man-days' to complete.
\n" ); document.write( "so 4 people would need 9 days to complete the same job because 36 = 4 times 9.
\n" ); document.write( "
\n" );