document.write( "Question 732335: The project described in the following table has just begun. It is scheduled to be completed in 15 weeks.
\n" ); document.write( "Use Table B1 and Table B2.\r
\n" ); document.write( "\n" ); document.write( "Activity Estimated Time
\n" ); document.write( "(weeks) Standard
\n" ); document.write( "Deviation (wks.)
\n" ); document.write( "1-2 5 0.73
\n" ); document.write( "2-4 6 0.66
\n" ); document.write( "1-3 4 0.60
\n" ); document.write( "3-4 9 1.85\r
\n" ); document.write( "\n" ); document.write( "a.
\n" ); document.write( "If you were the manager of this project, would you be concerned? (Round \"Probability\" values to 4 decimal places, intermediate calculations and final answers to 2 decimal places.)\r
\n" ); document.write( "\n" ); document.write( " because the probability of finishing on schedule is only about .\r
\n" ); document.write( "\n" ); document.write( "b.If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round \"Probability\" values to 4 decimal places, intermediate calculations and final answers to 2 decimal places.)\r
\n" ); document.write( "\n" ); document.write( " Probability
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #447776 by lynnlo(4176)\"\" \"About 
You can put this solution on YOUR website!
this is \"free tutoring,not to do all your homework,1 problem only \n" ); document.write( "