document.write( "Question 731980: If a piece of work could be completed in 24 days by 98 men how many men would it take to complete it in 21 days \n" ); document.write( "
Algebra.Com's Answer #447421 by Alan3354(69443)\"\" \"About 
You can put this solution on YOUR website!
If a piece of work could be completed in 24 days by 98 men how many men would it take to complete it in 21 days
\n" ); document.write( "----------------
\n" ); document.write( "The size of a job or project is often given in man-hours or man-days, the product of # of men * # of days
\n" ); document.write( "-----------
\n" ); document.write( "24*98 = 2352 man-days
\n" ); document.write( "---
\n" ); document.write( "2352 man-days/21 days = 112 men\r
\n" ); document.write( "\n" ); document.write( "
\n" ); document.write( "
\n" );