document.write( "Question 731980: If a piece of work could be completed in 24 days by 98 men how many men would it take to complete it in 21 days \n" ); document.write( "
Algebra.Com's Answer #447421 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! If a piece of work could be completed in 24 days by 98 men how many men would it take to complete it in 21 days \n" ); document.write( "---------------- \n" ); document.write( "The size of a job or project is often given in man-hours or man-days, the product of # of men * # of days \n" ); document.write( "----------- \n" ); document.write( "24*98 = 2352 man-days \n" ); document.write( "--- \n" ); document.write( "2352 man-days/21 days = 112 men\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |