document.write( "Question 682153: 18 boys can do a piece of work in 24 days. In how many days can the 27 boys do the same work?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #423060 by sachi(548)![]() ![]() You can put this solution on YOUR website! 18 boys can do a piece of work in 24 days \n" ); document.write( "so 1 boy can do the work in 24*18 days \n" ); document.write( "& 27 boys can do the work in 24*18/27=16 days \n" ); document.write( "In how 16 days can the 27 boys do the same work \n" ); document.write( " \n" ); document.write( " |