document.write( "Question 679129: if 9 employees require 15 days to complete a task, how long would it take to do the same work if there were 3 additional employees? \n" ); document.write( "
Algebra.Com's Answer #421820 by solver91311(24713)\"\" \"About 
You can put this solution on YOUR website!
\r
\n" ); document.write( "
\n" ); document.write( "\n" ); document.write( "If 9 take 15 days to do one whole job, then 9 can do of the job in one day. Then 1 can do of the job in one day. Then 12 can do of the job in 1 day. Therefore 12 can do the job in days.\r