document.write( "Question 601588: If 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days? \n" ); document.write( "
Algebra.Com's Answer #379893 by flame8855(424)![]() ![]() You can put this solution on YOUR website! 6 men in 14 days \n" ); document.write( "the rate is 6/14=3/7 men/day \n" ); document.write( "21 days so 3/7*21= 9 men needed \n" ); document.write( " \n" ); document.write( " |