document.write( "Question 584785: If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish building 4 houses.\r
\n" );
document.write( "\n" );
document.write( "Thanks. \n" );
document.write( "
Algebra.Com's Answer #372888 by scott8148(6628)![]() ![]() You can put this solution on YOUR website! 3 * 10 = 30 man-days per house\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "4 * 30 = 120 man-days for 4 houses\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "120 / 15 = 8 days \n" ); document.write( " |