document.write( "Question 541991: Joe took 4 hours to fill the pool and Jim took 6 hours to fill the pool. If they filled the pool at the same time how long would it take them? \n" ); document.write( "
Algebra.Com's Answer #354381 by stanbon(75887)\"\" \"About 
You can put this solution on YOUR website!
Joe took 4 hours to fill the pool and Jim took 6 hours to fill the pool. If they filled the pool at the same time how long would it take them?
\n" ); document.write( "-------
\n" ); document.write( "Joe rate: 1/4 job/hr
\n" ); document.write( "Jim rate: 1/6 job/hr
\n" ); document.write( "---
\n" ); document.write( "Together rate: 1/x job/hr
\n" ); document.write( "---
\n" ); document.write( "Equation:
\n" ); document.write( "rate + rate = together rate
\n" ); document.write( "1/4 + 1/6 = 1/x
\n" ); document.write( "3x + 2x = 12
\n" ); document.write( "5x = 12
\n" ); document.write( "x = 2.4 hrs (time to do the job together)
\n" ); document.write( "===============================
\n" ); document.write( "Cheers,
\n" ); document.write( "Stan H.
\n" ); document.write( "==============