document.write( "Question 522873: 6 chairs are made by 8 workers in 12 days. 50 chairs are made by 15 workers in how many days?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #347081 by ankor@dixie-net.com(22740) You can put this solution on YOUR website! 6 chairs are made by 8 workers in 12 days. \n" ); document.write( "Find no. of man-day required for each chair \n" ); document.write( " \n" ); document.write( ": \n" ); document.write( "50 chairs are made by 15 workers in how many days? \n" ); document.write( "Let d = no. of days to accomplish this \n" ); document.write( "15d = 50(16) \n" ); document.write( "15d = 800 \n" ); document.write( "d = \n" ); document.write( "d = 53 \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |