document.write( "Question 494362: It takes 4 men 14 days to do a certain job. How long should it take 7 men working at the same rate to do the same job? \n" ); document.write( "
Algebra.Com's Answer #335621 by Maths68(1474)\"\" \"About 
You can put this solution on YOUR website!
4 men do a job in…………………….14 days
\n" ); document.write( "Divide by 4 both sides
\n" ); document.write( "4/4 men do a job in…………………….14/4 days
\n" ); document.write( "1 man does the same job in ……..7/2 days
\n" ); document.write( "Multiply by 7 both sides
\n" ); document.write( "7*1 man does the same job in ……..7*(7/2) days
\n" ); document.write( "7 men will do the same job in …………..49/2 days
\n" ); document.write( "7 men will do the same job in …………..24 ½ days