document.write( "Question 479078: A can do a piece of work in 16 days and B can do it in 20 days. These worked together for 5 days and then B leaves in how many days will finish the semaining work. (Ans.7) \n" ); document.write( "
Algebra.Com's Answer #328276 by robertb(5830)![]() ![]() You can put this solution on YOUR website! \n" ); document.write( "\n" ); document.write( "<==> \n" ); document.write( "\n" ); document.write( "==> \n" ); document.write( "\n" ); document.write( "==> \n" ); document.write( "\n" ); document.write( "==> 5 + A = 12\r \n" ); document.write( "\n" ); document.write( "==> A = 7 days for A to finish the remaining work. \n" ); document.write( " |