document.write( "Question 478785: It takes 5 men to build a shed in 120 days, how long does it take 3 men? \n" ); document.write( "
Algebra.Com's Answer #328043 by Tatiana_Stebko(1539)\"\" \"About 
You can put this solution on YOUR website!
In 1 day 5 men do \"1%2F120\"part of job, so in 1 day 1 man does \"%281%2F120%29%2F5=1%2F600\" part of job, then 3 men will do in 1 day \"3%2A%281%2F600%29=1%2F200\" part of job, then all job they will do in \"1%2F%281%2F200%29=200\" days \n" ); document.write( "
\n" );