document.write( "Question 467347: if 4 men can mow certain piece of land in 6 days ,working 10 hours a day, how many days would it take 6men to mow the same land, if they worked 8 hours per day? \n" ); document.write( "
Algebra.Com's Answer #320648 by stanbon(75887)\"\" \"About 
You can put this solution on YOUR website!
if 4 men can mow certain piece of land in 6 days ,working 10 hours a day, how many days would it take 6 men to mow the same land, if they worked 8 hours per day?
\n" ); document.write( "-----
\n" ); document.write( "Note: 4 men take 60 hrs
\n" ); document.write( "---
\n" ); document.write( "# of men and time to do the job are indirectly related.
\n" ); document.write( "--------------------------
\n" ); document.write( "hrs = k/m
\n" ); document.write( "---
\n" ); document.write( "Solve for \"k\" using \"4 men take 60 hrs\"
\n" ); document.write( "60 = k/4
\n" ); document.write( "k = 240
\n" ); document.write( "-----
\n" ); document.write( "Equation:
\n" ); document.write( "days = 240/men
\n" ); document.write( "------------------------
\n" ); document.write( "Solve \"how many days would it take 6 men to mow the same land if they worked 8 hours per day?\"
\n" ); document.write( "---
\n" ); document.write( "hrs = 240/6
\n" ); document.write( "hrs = 40 hours
\n" ); document.write( "# of days = 40/8 = 5 days
\n" ); document.write( "=============================
\n" ); document.write( "Cheers,
\n" ); document.write( "Stan H.\r