document.write( "Question 444332: If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it?\r
\n" ); document.write( "\n" ); document.write( "A= .08 days
\n" ); document.write( "B= 1.9 days
\n" ); document.write( "C= 1.23 days
\n" ); document.write( "D= 1.65 days
\n" ); document.write( "E= 1.97 days
\n" ); document.write( "

Algebra.Com's Answer #306325 by jorel1380(3719)\"\" \"About 
You can put this solution on YOUR website!
1/4+1/6+1/2=?
\n" ); document.write( "3/12+2/12+6/12=?
\n" ); document.write( "11/12=1/x
\n" ); document.write( "12/11=x
\n" ); document.write( "It takes 12/11ths days for the three to complete a job..