document.write( "Question 425487: If 6 men can do a peice of work in 14 days, how many men are needed to do work in 21 days? \n" ); document.write( "
Algebra.Com's Answer #296261 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! 6 men * 14 days = 84 man-days \n" ); document.write( "M * 21 = 84 \n" ); document.write( "M = 4 men \n" ); document.write( " \n" ); document.write( " |