document.write( "Question 414469: Ho long will it take 6 workers to complete a task, give that 7 workers can complete the same task in 12 days \n" ); document.write( "
Algebra.Com's Answer #290698 by Edwin McCravy(20056)![]() ![]() You can put this solution on YOUR website! Ho long will it take 6 workers to complete a task, give that 7 workers can complete the same task in 12 days \n" ); document.write( " \r\n" ); document.write( "Since 7 workers can complete the task in 12 days, it would take\r\n" ); document.write( "one worker 7 times that long, and 7x12 = 84, so it would take one\r\n" ); document.write( "worker 84 days. It will take 6 workers only 1/6 as long as it would\r\n" ); document.write( "take one worker, and 1/6 of 84 is 14. So it will take 6 workers \r\n" ); document.write( "14 days to complete the task.\r\n" ); document.write( "\r\n" ); document.write( "Edwin\n" ); document.write( " |