document.write( "Question 413595: twelve workers can complete a job in six days. after working two days four workers are transferred to a new site. instead of six das, how many are required to complete the job \n" ); document.write( "
Algebra.Com's Answer #290213 by ewatrrr(24785)\"\" \"About 
You can put this solution on YOUR website!

\n" ); document.write( "Hi
\n" ); document.write( "twelve workers can complete a job in six days or 1/6 of job in 1 day.
\n" ); document.write( " \"%281%2F6%29%2F12\" = 1/72 by each worker each day.\r
\n" ); document.write( "\n" ); document.write( "After 2 days: 4/6 of job left and 8 workers left to complete:
\n" ); document.write( " 8/72 Or 1/9 per day \"%284%2F6%29%2F%281%2F9%29\" = 36/6 = 6 days to complete job \n" ); document.write( "