document.write( "Question 394478: A piece of work can be done in 48 days by 40 men. After 15 days, 16 men were transferred. In how many days can the remaining men finish the work? \n" ); document.write( "
Algebra.Com's Answer #280022 by jrfrunner(365)![]() ![]() You can put this solution on YOUR website! A piece of work can be done in 48 days by 40 men. After 15 days, 16 men were transferred. In how many days can the remaining men finish the work? \n" ); document.write( "== \n" ); document.write( "40 men can do the job in 48 days, this means that 40 men can do 1/48 of the job each hour \n" ); document.write( "- \n" ); document.write( "after 15 hours: 15/48 of the job is completed and 33/48=11/16 of the job incomplete \n" ); document.write( "- \n" ); document.write( "16 men are transferred. That leaves 24 men to complete the job. \n" ); document.write( "each man worked at a rate of 1/(48*40) (assuming they all work at the same rate). \n" ); document.write( "So the remaining 24 men work at the rate of 24/(48*40)=1/80 \n" ); document.write( "- \n" ); document.write( "11/16 of the job needs to be done by a crew of 24 working at a rate of 1/80 per hour. \n" ); document.write( "Job=rate *time or time =job/rate=(11/16)/1/80)=80*11/16=55hours\r \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |