document.write( "Question 389832: twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop work. in how many days can the rest finish the work? (Show Your Solution) \n" ); document.write( "
Algebra.Com's Answer #276388 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! twenty four men are engaged to do a piece of work in 38 days. after 10 days, 8 men stop work. in how many days can the rest finish the work? \n" ); document.write( "----------------- \n" ); document.write( "The job is 24*38 man-days = 912 man-days \n" ); document.write( "38*10 = 380 man-days done, 532 left \n" ); document.write( "532 man-days/16 men = 33.25 days \n" ); document.write( " \n" ); document.write( " |