document.write( "Question 370682: A and Bcan do a piece of work in 12 days, B and C in 10 days and A and C in 15 days. How long will each take to do work seprately
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #264255 by stanbon(75887)![]() ![]() ![]() You can put this solution on YOUR website! A and B can do a piece of work in 12 days, B and C in 10 days and A and C in 15 days. How long will each take to do work separately \n" ); document.write( "------------- \n" ); document.write( "Rate Equations: \n" ); document.write( "1/A + 1/B + 0 = 1/12 \n" ); document.write( "0 + 1/B + 1/C = 1/10 \n" ); document.write( "1/A + 0 + 1/C = 1/15 \n" ); document.write( "---- \n" ); document.write( "Using a matrix method I get: \n" ); document.write( "1/A = 1/40 \n" ); document.write( "1/B = 7/120 \n" ); document.write( "1/C = 1/24 \n" ); document.write( "=========== \n" ); document.write( "Days to do the job alone: \n" ); document.write( "A = 40 days \n" ); document.write( "B = 120/7 = 17.14 days \n" ); document.write( "C = 24 days \n" ); document.write( "===================== \n" ); document.write( "Cheers, \n" ); document.write( "Stan H.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |