document.write( "Question 357297: A team of 4 people has just finished half of a project in 10 days. If the rest of the project needs to be done in 5 more days, how many more people are needed? \n" ); document.write( "
Algebra.Com's Answer #255165 by Theo(13342) You can put this solution on YOUR website! i believe the assumption is that they all work at the same rate.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "right off the bat, i would say 8 people would be required.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "that's because twice as many people should be able to do the same work in half the time assuming that they all work at the same rate.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "a more formal approach would be as follows;\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Rate * Time = Units\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "The number of units is equal to 1 (the project).\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Since half the project was finished, then Units = .5\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Since the time it took was 10 days, then Time = 10\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "The formula becomes Rate * 10 = .5\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Divide both sides of this equation by 10 to get Rate = .5/10 which becomes:\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "Rate = .05 units per day.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "This means that 4 people work at the the rate of .05 of the project per day.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "10 * .05 = .5 which means that in 10 days 4 people finished half the project.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "if you divide the rate of 4 people by 4, then you get the rate of 1 person.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "the rate of 1 person becomes .05/4 = .125 of the project per day.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "The question is how many people are required to finish the project in another 5 days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "the same formula applies.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "rate * time = units\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "number of units = .5 (the other half of the project) \n" ); document.write( "time = 5 (the number of days required to finish the project).\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "the formula becomes:\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "rate * 5 = .5\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "divide both sides of the equation by 5 to get:\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "rate = .5/5 = .1\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "this means that .1 of the project needs to finished each day.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "the rate of each person is .125 of the project per day.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "multiply that by 8 and you get .1 of the project per day because 8 * .125 = 1.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "8 persons are required to finished the project in another 5 days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "the combined rate of the people is additive.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "if 1 person can do 1/2 of the project in one day and another person can do 1/2 of the project in 1 day, then both people will be able to complete the project in 1 day. each person working alone would take 2 days.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "same concept applies to this problem.\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "each person can finish .125 of the project in one day. \n" ); document.write( "8 persons can finish .1 of the project in one day. \n" ); document.write( "5 days total are required.\r \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( " \n" ); document.write( "\n" ); document.write( " \n" ); document.write( " |