document.write( "Question 351005: Ornery and sly company has a contract to dig a tunnel though bald mountain. Crew A start at the west end and digs at 9 meters per day . Let X be the number of days Crew A has been digging . Crew B starts at the east end two days after Crew A and digs at 12 meters per day.
\n" );
document.write( "a. show rate, tme and distance each crew has dug.
\n" );
document.write( "b. after how many days will the crews have dug the same distance?
\n" );
document.write( "c. The total length of the tunnel is to be 2000 meters . write an equation stating this fact. Then solve the equation to find out how many days it takes to dig the tunnel from the time Crew A starts. \n" );
document.write( "
Algebra.Com's Answer #250881 by stanbon(75887) ![]() You can put this solution on YOUR website! Ornery and sly company has a contract to dig a tunnel though bald mountain. \n" ); document.write( "------------------ \n" ); document.write( "Crew A start at the west end and digs at 9 meters per day . Let X be the number of days Crew A has been digging . \n" ); document.write( "--- \n" ); document.write( "show rate, tme and distance each crew has dug. \n" ); document.write( "distanceA = 9x meters \n" ); document.write( "time = x days \n" ); document.write( "rate = 9 meters per day \n" ); document.write( "----------------------- \n" ); document.write( "Crew B starts at the east end two days after Crew A and digs at 12 meters per day. \n" ); document.write( "--- \n" ); document.write( "show rate, tme and distance each crew has dug. \n" ); document.write( "distanceB = 12(x-2) = 12x-24 meters \n" ); document.write( "time = x-2 days \n" ); document.write( "rate = 12 meters per day \n" ); document.write( "-------------------------- \n" ); document.write( " \n" ); document.write( "b. after how many days will the crews have dug the same distance? \n" ); document.write( "Solve 9x = 12x-24 \n" ); document.write( "3x = 24 \n" ); document.write( "x = 8 days \n" ); document.write( "==================== \n" ); document.write( "c. The total length of the tunnel is to be 2000 meters . write an equation stating this fact. Then solve the equation to find out how many days it takes to dig the tunnel from the time Crew A starts. \n" ); document.write( "--- \n" ); document.write( "Equation: \n" ); document.write( "distanceA + distanceB = 2000 \n" ); document.write( "9x + 12x-24 = 2000 \n" ); document.write( "21x = 2024 \n" ); document.write( "x = 96.38 days \n" ); document.write( "====================== \n" ); document.write( "Cheers, \n" ); document.write( "Stan H. \n" ); document.write( " \n" ); document.write( " |