document.write( "Question 351005: Ornery and sly company has a contract to dig a tunnel though bald mountain. Crew A start at the west end and digs at 9 meters per day . Let X be the number of days Crew A has been digging . Crew B starts at the east end two days after Crew A and digs at 12 meters per day.
\n" ); document.write( "a. show rate, tme and distance each crew has dug.
\n" ); document.write( "b. after how many days will the crews have dug the same distance?
\n" ); document.write( "c. The total length of the tunnel is to be 2000 meters . write an equation stating this fact. Then solve the equation to find out how many days it takes to dig the tunnel from the time Crew A starts.
\n" ); document.write( "

Algebra.Com's Answer #250881 by stanbon(75887)\"\" \"About 
You can put this solution on YOUR website!
Ornery and sly company has a contract to dig a tunnel though bald mountain.
\n" ); document.write( "------------------
\n" ); document.write( "Crew A start at the west end and digs at 9 meters per day . Let X be the number of days Crew A has been digging .
\n" ); document.write( "---
\n" ); document.write( "show rate, tme and distance each crew has dug.
\n" ); document.write( "distanceA = 9x meters
\n" ); document.write( "time = x days
\n" ); document.write( "rate = 9 meters per day
\n" ); document.write( "-----------------------
\n" ); document.write( "Crew B starts at the east end two days after Crew A and digs at 12 meters per day.
\n" ); document.write( "---
\n" ); document.write( "show rate, tme and distance each crew has dug.
\n" ); document.write( "distanceB = 12(x-2) = 12x-24 meters
\n" ); document.write( "time = x-2 days
\n" ); document.write( "rate = 12 meters per day
\n" ); document.write( "--------------------------
\n" ); document.write( "
\n" ); document.write( "b. after how many days will the crews have dug the same distance?
\n" ); document.write( "Solve 9x = 12x-24
\n" ); document.write( "3x = 24
\n" ); document.write( "x = 8 days
\n" ); document.write( "====================
\n" ); document.write( "c. The total length of the tunnel is to be 2000 meters . write an equation stating this fact. Then solve the equation to find out how many days it takes to dig the tunnel from the time Crew A starts.
\n" ); document.write( "---
\n" ); document.write( "Equation:
\n" ); document.write( "distanceA + distanceB = 2000
\n" ); document.write( "9x + 12x-24 = 2000
\n" ); document.write( "21x = 2024
\n" ); document.write( "x = 96.38 days
\n" ); document.write( "======================
\n" ); document.write( "Cheers,
\n" ); document.write( "Stan H.
\n" ); document.write( "
\n" ); document.write( "