document.write( "Question 348900: Construction A roofer requires 12 hours to shingle a roof. After the
\n" );
document.write( "roofer and an apprentice work on a roof for 3 hours, the roofer moves
\n" );
document.write( "on to another job. The apprentice requires 12 more hours to finish the
\n" );
document.write( "job. How long would it take the apprentice, working alone, to do the job?
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #249398 by scott8148(6628)![]() ![]() You can put this solution on YOUR website! in the 3 hours that the roofer worked , he completed 1/4 of the job (3/12)\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "that means it takes the apprentice 15 hr (3+12) to do 3/4 of the job \n" ); document.write( " |