document.write( "Question 347863: please answer sir,ma'am\"mark contracted 15 skilled workers to finish cementing a certain walk of uniform width in 16 days.after 8 days of work,6 of them got sick and were not replaced until 4 days after.he wants the job to be on time .how many should he hire?\"\r
\n" ); document.write( "\n" ); document.write( "thank you
\n" ); document.write( "

Algebra.Com's Answer #248716 by Fombitz(32388)\"\" \"About 
You can put this solution on YOUR website!
Originally, the job required \"15%2A16=240\" worker-days to complete.
\n" ); document.write( "They put in \"15%2A8=120\" worker-days in 8 days.
\n" ); document.write( "The reduced crew of \"11\" put in \"11%2A4=44\" worker-days in 4 days.
\n" ); document.write( "Look at the worker-days remaining.
\n" ); document.write( "\"W%2AD%2B44%2B120=240\"
\n" ); document.write( "\"W%2AD%2B164=240\"
\n" ); document.write( "\"W%2AD=76\"
\n" ); document.write( ".
\n" ); document.write( ".
\n" ); document.write( ".
\n" ); document.write( "76 worker-days of output are required to finish the job.
\n" ); document.write( "He has used up \"8%2B4=12\" days aleready and he has 4 days if he wants to stick to the 16 day schedule.
\n" ); document.write( "\"W%2A4=76\"
\n" ); document.write( "\"W=19\"
\n" ); document.write( "He needs to have \"19\" workers to make his schedule.
\n" ); document.write( "Since he's already hired \"11\" workers, he should hire an additional \"highlight%288%29\" workers.