document.write( "Question 344668: it required 75 men 38 days to build a flood control dike. if 18 less men were employed, how much longer would it have taken to build the dike? show the solution. \n" ); document.write( "
Algebra.Com's Answer #246618 by Fombitz(32388)\"\" \"About 
You can put this solution on YOUR website!
You need \"75%2A38\" or \"2850\" man-days to complete the dike.
\n" ); document.write( "If you only have (\"75-18\")\"57\" men, then it would take,
\n" ); document.write( "\"N=2850%2F57=50\" days to complete or (\"50-38\")\"12\" days longer.
\n" ); document.write( "
\n" ); document.write( "
\n" );