document.write( "Question 310372: The number of days it takes to complete a job varies inversely as the number of people assigned to the job. It if takes 7 people, 8 days to complete the job, how long will it take 10 people to complete the job? \n" ); document.write( "
Algebra.Com's Answer #221990 by ankor@dixie-net.com(22740)![]() ![]() You can put this solution on YOUR website! The number of days it takes to complete a job varies inversely as the number of \n" ); document.write( " people assigned to the job. \n" ); document.write( "It if takes 7 people, 8 days to complete the job, how long will it take 10 people to complete the job? \n" ); document.write( ": \n" ); document.write( "Let t = time required using 10 men \n" ); document.write( ": \n" ); document.write( "Inverse ratio equation \n" ); document.write( " \n" ); document.write( "Cross multiply \n" ); document.write( "10t = 56 \n" ); document.write( "t = \n" ); document.write( "t = 5.6 days with 10 men working \n" ); document.write( " |