25 workers could finish a job in 8 days. 2 days into the job, 7 leave. how long will it take for the remaining 18 to finish the job?
\n" ); document.write( "--------------
\n" ); document.write( "The job is 200 man-days (igoring age and gender)
\n" ); document.write( "25*2 = 50, leaving 150 man-days
\n" ); document.write( "150/18 = 25/3 days