document.write( "Question 300784: The amount of time taken to build a house is inversely proportional to the
\n" );
document.write( "number of construction workers on the job. If it takes 6 workers 6 days to complete such a job, how many days will it take if the job is done by only 4 workers? \n" );
document.write( "
Algebra.Com's Answer #215743 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! 6 men * 6 days = 36 man-days \n" ); document.write( "36 man-days/4 men = 9 days \n" ); document.write( " \n" ); document.write( " |