document.write( "Question 294873: plz help to solve this problem;Jim and Carry can do a piece of work in 8 days and 16 days respectively. They start working together, but Jim quits 6 days before the job is done. In what time is the job completed? \n" ); document.write( "
Algebra.Com's Answer #212586 by richwmiller(17219)![]() ![]() You can put this solution on YOUR website! x/8+x/16=1 \n" ); document.write( "multiply by 16 \n" ); document.write( "2x+x=16 \n" ); document.write( "3x=16 \n" ); document.write( "x=16/3 \n" ); document.write( "Together they can do the job in 16/3 or 5 1/3 days \n" ); document.write( "There is something wrong. Jim the faster worker quit the day before they started. \n" ); document.write( "So it will take Carry 16 days to do the job. \n" ); document.write( " \n" ); document.write( " |