document.write( "Question 270311: There are 3 tunnels each 50 kilometers long, and each tunnel has a boring machine at each end working towards each other. the 6 boring machines are capable of moving upto 78 metres per day.....If all 6 boring machines was working at full capacity, how long would it take to dig through the tunnels.\r
\n" ); document.write( "\n" ); document.write( "I make it 106.8 days, but I think I am wrong?????????????????
\n" ); document.write( "

Algebra.Com's Answer #198053 by Alan3354(69443)\"\" \"About 
You can put this solution on YOUR website!
Each tunnel has a machine at each end.
\n" ); document.write( "50000/2*78 =~ 320.5 days
\n" ); document.write( "
\n" ); document.write( "