document.write( "Question 259777: If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it? how to solve, explain please
\n" );
document.write( " \n" );
document.write( "
Algebra.Com's Answer #191236 by Alan3354(69443)![]() ![]() You can put this solution on YOUR website! If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it? how to solve, explain please\r \n" ); document.write( "\n" ); document.write( "------------- \n" ); document.write( "In one day, \n" ); document.write( "Sam does 1/4 \n" ); document.write( "Lisa does 1/6 \n" ); document.write( "Tom does 1/2 \n" ); document.write( "------------- \n" ); document.write( "1/4 + 1/6 + 1/2 = 11/12 per day together \n" ); document.write( "--> 12/11 days to do the job. \n" ); document.write( " \n" ); document.write( " |