document.write( "Question 259777: If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it? how to solve, explain please
\n" ); document.write( "
\n" ); document.write( "

Algebra.Com's Answer #191236 by Alan3354(69443)\"\" \"About 
You can put this solution on YOUR website!
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it? how to solve, explain please\r
\n" ); document.write( "\n" ); document.write( "-------------
\n" ); document.write( "In one day,
\n" ); document.write( "Sam does 1/4
\n" ); document.write( "Lisa does 1/6
\n" ); document.write( "Tom does 1/2
\n" ); document.write( "-------------
\n" ); document.write( "1/4 + 1/6 + 1/2 = 11/12 per day together
\n" ); document.write( "--> 12/11 days to do the job.