document.write( "Question 255211: team A and team B build houses.If the teams work together they can build a house in 4 days. Team A working alone can complete a house in 10 days.If the team works together for 3 days, but then team B Leaves, how much longer will team A need to finish the house? yuck! \n" ); document.write( "
Algebra.Com's Answer #187509 by edjones(8007)![]() ![]() You can put this solution on YOUR website! Yuk? Roll up your sleeves, we've got work to do! \n" ); document.write( "Together they do 1/4 the job in 1 day. \n" ); document.write( "A does 1/10 job in 1 day. \n" ); document.write( ". \n" ); document.write( "Together the do 3/4 the job in 3 days. \n" ); document.write( "There is 1/4 of the job left to do. How many 1/10 make 1/4? Let a=number of days left. \n" ); document.write( "a/10=1/4 \n" ); document.write( "a=10/4=5/2=2.5 days for team A to finish the job. \n" ); document.write( "Easy, no ifs, ands or yuks about it. \n" ); document.write( ". \n" ); document.write( "Ed \n" ); document.write( " |