document.write( "Question 31641: Alan and Jim were asked by their boss to work on a project. Since Jim had to visit a company's factory outside of the state, Alan started the project alone. After 10 days Jim came back and they worked for 5 days to finish the project. If Alan could have finished the project in 23 days when Alan worked alone from the beginning to the end, how long would it take if Jim had to work alone from the bedid to the end to finish the project? Your answer is supposed to be d days and h hours where d is a positive integer and h is a positive integer or 0. \n" ); document.write( "
Algebra.Com's Answer #18285 by mukhopadhyay(490)![]() ![]() ![]() You can put this solution on YOUR website! Alan can finish the same job in 23 days \n" ); document.write( "=> Alan completes 1/23 portion of the job in 1 day \n" ); document.write( "Alan worked by himself for 10 days and he aslo spent an additional 5 days with Jim to finish the job \n" ); document.write( "So, Alan spent a total of 15 days for the project \n" ); document.write( "In 15 days, Alan did 15/23 portion of the job \n" ); document.write( "The remaining 8/23 (1 - 15/23) portion of the job was done by Jim in 5 days \n" ); document.write( "Jim does 8/23 portion of the job is 5 days \n" ); document.write( "=> Jim does 1 job is 5*(23/8) = 115/8 days \n" ); document.write( "115/8 days = 14 and 3/8 days = 14 days and 24(3/8) hours = 14 days and 9 hours \n" ); document.write( "So, if Jim had to finish the project from start to end all by himself, it would have taken him 14 days 9 hours to do so. \n" ); document.write( " \n" ); document.write( " |