document.write( "Question 204106: If 6 men can do a piece of work in 14 days, how many men are needed to do work in 21 days? \n" ); document.write( "
Algebra.Com's Answer #154045 by scott8148(6628)![]() ![]() You can put this solution on YOUR website! it takes 84 man-days (6 * 14) to do the job\r \n" ); document.write( " \n" ); document.write( "\n" ); document.write( "to do the job in 21 days would take 4 men (84 / 21) \n" ); document.write( " |