document.write( "Question 202651: A crew of 6 can complete a job in 8 hours. How many hours would it take a group of 4 to complete the job? \n" ); document.write( "
Algebra.Com's Answer #152844 by vleith(2983)\"\" \"About 
You can put this solution on YOUR website!
This a really poor question. It is quite possible that a job that can be done by 6 people, cannot be done by 4 people no matter what the job is. Also, there is nothing to let you know if the 4 person group is subset of the 6. So perhaps the skills held by the 6 person group are not skills the 4 person group has.\r
\n" ); document.write( "\n" ); document.write( "That said, I am sure the intent is as follows:
\n" ); document.write( "The job requites 6*8= 48 person/hours
\n" ); document.write( "If there are 4 people working, the 48/4 = 12. So the group of 4 will take 12 hours to complete the job.
\n" ); document.write( "
\n" ); document.write( "
\n" );