document.write( "Question 176395: If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how long would the job take if Sam, Lisa, and Tom worked together to complete it? \n" ); document.write( "
Algebra.Com's Answer #131491 by Mathtut(3670)![]() ![]() ![]() You can put this solution on YOUR website! sam can do 1/4 of the job per day \n" ); document.write( "lisa can do 1/6 of the job per day \n" ); document.write( "tom can do 1/2 of the job per day \n" ); document.write( ": \n" ); document.write( "together they can do \n" ); document.write( ": \n" ); document.write( " \n" ); document.write( ": \n" ); document.write( " \n" ); document.write( ": \n" ); document.write( " \n" ); document.write( ": \n" ); document.write( "so 11/12t=1(job) \n" ); document.write( ": \n" ); document.write( "t=12/11 days \n" ); document.write( " |