document.write( "Question 163802: Three workers set out to plaster a ceiling. One can do the job alone in 2 hours, one in three hours and the last in 4 hours how long does it take them together to plaster the ceiling? \n" ); document.write( "
Algebra.Com's Answer #120668 by edjones(8007)![]() ![]() You can put this solution on YOUR website! One can do 1/2 the job in 1 hr, another 1/3 and another 1/4 the job in 1 hr. \n" ); document.write( "1/2 + 1/3 + 1/4 \n" ); document.write( "=6/12 + 4/12 + 3/12 \n" ); document.write( "=13/12 of the job in 1 hr together \n" ); document.write( "12/13 of an hour to do the job working together. \n" ); document.write( ". \n" ); document.write( "Ed \n" ); document.write( " |