Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 day?
It'll take men, working 8 days, @ 10 hours each day, or 80 hours to complete the remaining of job