SOLUTION: Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many men working at the same rate and for the same number of hours each day, will be required to c

Algebra.Com
Question 1019528: Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 day?
Found 2 solutions by robertb, MathTherapy:
Answer by robertb(5830)   (Show Source): You can put this solution on YOUR website!
The total number of man hours (for the first 6 days) required to finish 5/21 of the work is 10*6*10 = 600 man-hours. Hence each man contributes for the entire job.
Now 16/21 of the job still had to be done, and the job had to be done at the same rate and at the same number of hours each day.
Note that 16/21 of the job had to be completed in 2 more days. (2 additional days after initial 6 days.)
Let m = number of men required to complete the job in two more days
Hence...

==>
==> m = 96.
Therefore it will take 96 men to finish the job in two more days at the same rate and same number of hours each day.

Answer by MathTherapy(10552)   (Show Source): You can put this solution on YOUR website!

Ten men working for 6 days of 10 hours each, finish 5/21 of a piece of work . How many men working at the same rate and for the same number of hours each day, will be required to complete the remaining work in 8 day?
It'll take  men, working 8 days, @ 10 hours each day, or 80 hours to complete the remaining  of job 

RELATED QUESTIONS

10 men working for 6 days of 10 hours each finish 5/21 of a piece of work. How many men... (answered by richwmiller)
Ten Men take 12 days to handle a certain work.How many men working at the same rate do... (answered by trinityhollins0)
20 men can do a piece of work in 24 days. After working for 6 days, additional number of... (answered by richwmiller)
15 men take 21 days of 8 hours each to do a piece of work. How many days of 6... (answered by richwmiller)
if 9 men can do a piece of work for 20 days, how long would it take 4 men to do do,... (answered by josgarithmetic)
15 men working 7 hours a day can finish a piece of work in 15 days. How many days will... (answered by ankor@dixie-net.com)
if four men do a piece of work in 8 days how many days will it take 16 men working at the (answered by ewatrrr)
If 10 men can make 200 tables working for 15 days at the rate of 8 hr per day, how many... (answered by Edwin McCravy)
10 men can do a piece of work in 24 days. After working 6 days,few men were added to... (answered by Edwin McCravy)