Question 968541: Suppose that it takes 9 hours for four workers to roof a house. If the time required to do the job
varies inversely as the number of people working on it, how long does it take for five workers to finish a
roof of the same size?

Answer by ankor@dixie-net.com(22740)   (Show Source): You can put this solution on YOUR website!
Suppose that it takes 9 hours for four workers to roof a house.
If the time required to do the job varies inversely as the number of people working on it, how long does it take for five workers to finish a
roof of the same size?
:
let t = time required by 5 men to do the job
An inverse relationship
=
Cross multiply
5t = 36
t = 36/5
t = 7.2 hrs fro 5 men to do the job

RELATED QUESTIONS

The time it takes to complete a certain job varies inversely as the number of people... (answered by josgarithmetic)
The time required to accomplish a task varies inversely as the number of people working... (answered by ptaylor)
The number of workers is required to complete a job varies inversely as the time spent... (answered by josgarithmetic)
The number of workers n needed to clean a stadium after a game varies inversely as the... (answered by stanbon)
Inverse variation, Solve following problem 1. The time t required to do a job varies... (answered by math_helper,Theo)
The time T to do a job varies inversely as the number of people P working. It takes... (answered by richwmiller)
the time it takes to complete a certain job varies inversely to the number of people... (answered by stanbon)
The time T required to do a job varies inversely as the number of people P working. It... (answered by mananth)
the time t required to do a certain job varies inversely as the number of people in... (answered by ankor@dixie-net.com)