Question 926630: A homeowner estimates that it will take her 9 days to roof her house. A professional roofer estimates that he could roof the house in 4 days. How long will it take if the homeowner helps the roofer?
Answer by Alan3354(69443)   (Show Source): You can put this solution on YOUR website!
A homeowner estimates that it will take her 9 days to roof her house. A professional roofer estimates that he could roof the house in 4 days. How long will it take if the homeowner helps the roofer?
=================
The owner does 1/9 of the roof per day.
The roofer does 1/4 of the roof per day.
Can you do the rest?

RELATED QUESTIONS

a homeowner estimates that it will take her 9 days to roof her house. A professional... (answered by HyperBrain,Alan3354)
A homeowner estimates that it will take her 7 days to roof her house. A professional... (answered by richwmiller)
A homeowner estimates that it will take her 7 days to roof her house. A professional... (answered by josgarithmetic)
A homeowner estimates that it will take 9 days to roof his house. A professional roofer... (answered by richwmiller,josgarithmetic)
A homeowner estimates that it will take him 13 days to roof his house. A professional... (answered by checkley79)
A homeowner estimates that it will take him 8 days to roof his house. A professional... (answered by josmiceli)
If one professional roofer can roof and house in six days and another roofer can do it in (answered by ptaylor)
Mary can roof her house in 7 days working alone. Her husband can roof their house in 14... (answered by richwmiller)
Mary can roof their house in 4 days working alone, her husband can roof their house in 6... (answered by josmiceli)