Question 646678: A,B,C can finish a piece of work in 60 days. They work together for 10 days after which A leaves, B and C continue for 20 days more days, after which B leaves. then C working for one-third longer each day completes the remaining work in 96 more days. If C had been working working at its own original rate then he would have completed the work in 222 days. How long would B take?
Answer by htmentor(1343) (Show Source): You can put this solution on YOUR website!
Let a, b, c be the three work rates
Working together, they can complete the job in 60 days:
a + b + c = 1 job/60 d = 1/60
After 10 days, the job is (1/60)*10 = 1/6 complete
B and C working together for 20 days complete this much of the job: 20(b+c)
Then C working alone completes the job in 96 days working 4/3 as much per day.
So C completes this much of the job: 96c(4/3) = 128c
C working alone can complete the job in 222 days, so c = 1/222
Since after the first 10 days 5/6 of the job gets completed, we can write:
5/6 = 128c + 20(b+c)
5/6 = 128/222 + 20b + 20/222
Simplifying gives 5/6 = 4/6 + 20b
b = (1/6)/20 = 1/120
So B can complete the job in 120 days
RELATED QUESTIONS
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
A does 3/10 of a work in 6 days .He then calls in B and they finish the work in 7 days... (answered by ankor@dixie-net.com)
A can do a piece of work in 25 days and B can do a work in 20 days.both work together... (answered by ptaylor)
Person A can do a piece of work in 10 days. After he has worked for 2 days, B comes and... (answered by scott8148)
A can do a piece of work in 16 days and B can do it in 20 days. These worked together for (answered by robertb)
A can do a piece of work in 9 days, B in 12 days and C in 18 days. A & B work for 3 days... (answered by ewatrrr,ankor@dixie-net.com)
A can do a piece of work in 20 days which B can do it in 12 days. B worked at it for 9... (answered by mananth)
A and B can do a piece of work in 42 days, B and C in 31 days, and A and C in 20 days.... (answered by ptaylor,Edwin Parker)
three men A,B and C can complete a job in 8,12,16 days respectively. A , B can work... (answered by Theo)