SOLUTION: A can do a work in 32 days and B in 40 days. they work together for 10 days and then B left. In how many days A will finish the remaining work??
Algebra.Com
Question 320330: A can do a work in 32 days and B in 40 days. they work together for 10 days and then B left. In how many days A will finish the remaining work??
Answer by mananth(16946) (Show Source): You can put this solution on YOUR website!
A can do a work in 32 days and B in 40 days. they work together for 10 days and then B left. In how many days A will finish the remaining work?
A does 1/32 of the job in 1 day
B does 1/40 of the job in 1 day
..
Together they do 1/32 +1/40 in 1 day
= 72/1280 of the job in 1 day.
In 10 days they do 72/1280 * 10
=72/128.
..
balance work will be 1- 72/128
128-72 / 128
=56 /128
=7/16
1/32 of the job A does in 1 day
7/16 of the job he will do 7/16 / 1/32
=7/16 *32
= 14 days
A will take 14 more days to complete the job.
...
RELATED QUESTIONS
A can do a work in 32 days and B in 40 days. they work together for 10 days and then B... (answered by edjones)
2 persons a and b they can complete a certain work in 16 and 20 days they work together... (answered by anand429)
A can build a room in 50 days. A & B together can build a room in 25 days. They worked... (answered by macston)
A can do a piece of work in 16 days and B can do it in 20 days. These worked together for (answered by robertb)
A,B and C can do a piece of work together in 15 days. B alone can do in 30 days and C... (answered by ankor@dixie-net.com)
A can do 1/3 of certain work in 10 days and B can do 2/5 of the same work in 8 days find... (answered by robertb)
Joel can finish a work in 10 days, after he has worked for 2 days, Sam came to help him... (answered by richwmiller)
Worker A can do a piece of work in 20 days. Workers A and B in 15 days.
They work... (answered by richwmiller)
A, B, & C can do a piece of work in 10, 9, 15 days respectively. They started the work... (answered by richwmiller)