SOLUTION: One carpenter can complete a kitchen in 8 days. With the help of another carpenter, they can do the job together in 4 days. How long would it take the second carpenter if he work
Algebra.Com
Question 105584: One carpenter can complete a kitchen in 8 days. With the help of another carpenter, they can do the job together in 4 days. How long would it take the second carpenter if he worked alone?
Answer by askmemath(368) (Show Source): You can put this solution on YOUR website!
If the carpenter takes 8days to finish the job, in 1 day he will do of work.
Similary let the other carpenter take a days to finish the job therefore he will in one day do of the work
Combined in one day they will do of the work in day
But we know that combined they take 4days to finish the job.SO in 1day they should do 1/4 of the work
Can you solve for a?
RELATED QUESTIONS
One carpenter can complete a kitchen in 8 days. With the help of another carpenter, they (answered by stanbon)
One carpenter can complete a kitchen in 8 days. With the help of another carpenter, they (answered by scott8148)
One group of workers can do a job in 8 days. After this group has worked 3 days, another... (answered by mangopeeler07)
One group of workers can do a job in 8 days. After this group has worked 3 days, another... (answered by ankor@dixie-net.com)
One group of workers can do a job in 8 days. After this group has worked 3 days, another... (answered by josmiceli)
A carpenter and a helper can do a certain job in 24 days. If the carpenter works 1.50... (answered by mananth)
A Carpenter and a helper can do a certain job in 15 days. If the Carpenter works 1.5... (answered by josgarithmetic,MathTherapy,richwmiller)
A carpenter and a helper can do a certain job in 18 days. If the carpenter works 1.50... (answered by Boreal)
A can do a job in 6 days while B can do a job in 8 days. They worked together for 2 days... (answered by richwmiller)