Question 103228: Please help me! Thank you.
This is from a worksheet:
Crew A and Crew B are digging a tunnel. Crew A starts at the west end and digs at a rate of 9 meters a day. Crew B starts 2 days later at the east end at the rate of 12 meters per day. How many days will it take for both crews to dig the same number of meters? The length of the tunnel is to be 2118 meters. How many days does it take to dig the tunnel from when Crew A starts?

Answer by scott8148(6628)   (Show Source): You can put this solution on YOUR website!
let x=time for equal distance ... 9x=12(x-2) ... 9x=12x-24 ... -3x=-24 ... x=8

let y=time for completion ... 9y+12(y-2)=2118 ... 9y+12y-24=2118 ... 21y=2142 ... y=102

RELATED QUESTIONS

two crews are digging an 8-meter tunnel through marble mountain. crew A starts at the... (answered by Alan3354)
Two crews are digging an 800-meter tunnel through Marble Mountain. Crew A starts at the... (answered by ankor@dixie-net.com)
Ornery and sly company has a contract to dig a tunnel though bald mountain. Crew A start... (answered by stanbon)
Losing my mind here...please help. Both crew A and Crew B can lay underground cable at (answered by mbarugel)
a construction crew (answered by ikleyn)
I am having trouble trying to figure out how to work this probability problem. Could... (answered by stanbon)
a crew of eight can row 20 kilometers per hour in still water. The crew rows upstream... (answered by ankor@dixie-net.com)
A crew of 8 can row 20 kilometers/hour in still water. The crew rows upstream and then... (answered by scott8148)
A crew can row 8km downstreat and back in 4.8 hours. If the rate of the current is 4... (answered by venugopalramana)