Question 900941: Ed can do a job in 4 days. When Ed and Maymay work together, it would take them 2 1/2 days. How long would the job take maymay to do the job alone?
Answer by richwmiller(17219)   (Show Source): You can put this solution on YOUR website!
rate for A alone 4
rate for A & B together 2.5
1/a+1/b=1/x
1/4+1/b=1/2.5
1/b=1/2.5-1/4
1/b=4/10.0-2.5/10.0
1/b=1.5/10.0
1/b=1/6.66666667
b=6.66666667
rate for B alone 6.66666667

RELATED QUESTIONS

Ed can do a job in 4 days. When Ed and Maymay work together, it would take them 2 1/3... (answered by ankor@dixie-net.com)
Ed can do a job in 4 days. When Ed and Maymay work together, it would take them 2 1/3... (answered by mananth)
Ed can do a job in 4 days. when ed and maymay work together, it would take them 2 and 1/3 (answered by MathLover1)
1. One half of a number is 3 more than one sisxth of the same number. What is the number? (answered by solver91311,ankor@dixie-net.com)
If Sam can do a job in 4 days that Lisa can do in 6 days and Tom can do in 2 days, how... (answered by ptaylor)
If sam can do a job in 4 days that Lisa can do in 6 days, and Tom can do in 2 days, how... (answered by nerdybill)
urgent.. working together, alice and betty can do a certain job in 4 1/3 days. but alice (answered by ptaylor)
working together, alice and betty can do a certain job in 4 1/3 days. but alice fell ill... (answered by ankor@dixie-net.com)
Working together, Alice and Betty can do a certain job in 4 1/3 days. But Alice fell ill... (answered by stanbon)