SOLUTION: 25 women did 1/5 of job in 8 days. Then, because of an emergency, it became necessary to complete the job in the next 20 days. How many additional women needed to be added to the c

Algebra.Com
Question 696514: 25 women did 1/5 of job in 8 days. Then, because of an emergency, it became necessary to complete the job in the next 20 days. How many additional women needed to be added to the crew of 25 to accomplish this?
Answer by Edwin McCravy(20056)   (Show Source): You can put this solution on YOUR website!
25 women did 1/5 of job in 8 days. Then, because of an emergency, it became necessary to complete the job in the next 20 days. How many additional women needed to be added to the crew of 25 to accomplish this?
I'll show you two ways to do this:

25 women can do 1/5 of the job in 8 days. Therefore, 
25 women can do the whole job in 40 days. Therefore,
50 women can do the whole job in 20 days. Therefore,
since only 4/5th of the job needs completing, it will
only take 4/5ths of 50 women to do the remaining 4/5ths
of the job, and 4/5ths of 50 is 40.  They already have
25 women, so they'll need 40-25 or 15 more women. 


Another way to do this is with the worker-time-job formula, which is:



where

W1 = the number of workers in the first situation.
T1 = the number of time units (days in this case) in the first situation.
J1 = the number of jobs (or fraction thereof) in the first situation.

W2 = the number of workers in the second situation.
T2 = the number of time units (days in this case) in the second situation.
J2 = the number of jobs (or fractionthereof) in the second situation.

W1 = 25             W2 = the unknown quantity     
T1 =  8             T2 = 20 
J1 = 1/5            J2 = 4/5







To divide by a fraction, invert it and multiply:













 40 = W2 

So it will take a total of 40 workers.  There are already 25 workers,
so it will take 40-25 = 15 more workers.

Answer: 15 more workers.

Edwin

RELATED QUESTIONS

Twenty men did 1/4 of a job in 8 days. Then, because of an emergency, it became necessary (answered by ankor@dixie-net.com)
Twenty men did 1/4 of a job in eight days. Then it became necessay to complete the job... (answered by ankor@dixie-net.com)
Ten workers could do the job in 12 days. If 8 workers worked for 5 days and then half of... (answered by ankor@dixie-net.com)
Hi 10 men and 20 women can do a job in 15 days. 15 men and 10 women can do the same job... (answered by VFBundy)
If a job can be completed by 2 workers in 10 days, then what is the number of workers... (answered by stanbon)
If 15 workers can complete a job in 20 days, how long should it take 25 workers to... (answered by ankor@dixie-net.com)
If 12 men and 10 women can complete a job in 15 day, how many days will it take for 30... (answered by ikleyn)
5 men are hired to complete a certain job. if an additional men is hired, the job can be... (answered by ikleyn)
1.'A' works twice as fast as 'B'. If both of them together take 6 days to complete the... (answered by josmiceli,vvnrichards)