SOLUTION: •Model A takes 2 hours to assemble. •Model B takes 3 hours to assemble. •Model A costs $25 to make per bike. •Model B costs $30 to make per bike. If your company has a total o

Algebra.Com
Question 330597: •Model A takes 2 hours to assemble.
•Model B takes 3 hours to assemble.
•Model A costs $25 to make per bike.
•Model B costs $30 to make per bike.
If your company has a total of 34 hours and $350 available per day for these two models, how many of each model can be made in a day?
•Solve the equations for the different bicycle models that can be made daily with the desired technique learned (graphing, substitution, elimination, and matrix).
•Explain how to check your solution for both equations.

Answer by Fombitz(32388)   (Show Source): You can put this solution on YOUR website!
Previously answered.
.
.
.
Let A be the number of Model A's and B be the number of model B's.
Time Available
1.
.
.
Money available

2.
.
.
.
Let A be represented by the x axis and B by the y axis.
Plot line 1, and plot line 2, and find the intersection point when


and
.
.
.

.
.
.
The company could assemble any combination of A and B within the blue box with vertices:(0,0),(0,34/3),(2,10),(14,0).
As an example, , would work. However they would have hours and money left over.
If they want to use exactly $350 and 34 hours, then the only solution is ,

RELATED QUESTIONS

Model A takes 2 hours to assemble Model B takes 3 hours to assemble Model A costs $25... (answered by Fombitz)
Your company produces two models of bicycles: Model A and Model B. Model A takes 2 hours... (answered by stanbon)
your company produces two models of bikes Model A and Model B Model A takes 2 hours to... (answered by ankor@dixie-net.com)
please help i dont understand how to do this •Model A takes 2 hours to assemble.... (answered by mananth)
How do I set this problem up to solve and check? A company produces 2 model bikes; Model (answered by Theo)
Model A takes 2 hours to assemble. Model B takes 3 hours to assemble. Model A costs $25 (answered by Fombitz)
Your company produces two models of bicycles: Model A and Model B. Model A takes 2... (answered by ankor@dixie-net.com)
Model A takes 2hours to assemble and cost $25 per bike, to make. Model B takes 3hours to (answered by mananth)
As a business owner I have to make many decisions on a daily basis to ensure that my... (answered by stanbon)