Three masons build of wall. Mason A builds 7.0m/day , B builds 6.0m/day , and C builds5.0 m/day . Mason B works twice as many days as A , and C works half as many days as A and B combined. How many days did each work?
The masons built 318 m of wall. This was OMITTED.
Let number of days A worked be D
Then number of days B worked = 2D
Number of days C worked =
Amounts built by A, B, and C are: 7D, 6(2D), or 12D, and , respectively
Since a 318-meter wall was built, we get:
38D + 15D = 636 ------- Multiplying by LCD, 2
53D = 636
D, or number of days A worked = , or
Number of days B worked: 2(12), or
Number of days C worked: , or